• LECA PRODUCTION LINE
  • MAGNESIUM PRODUCTION LINE
  • ACTIVE LIME PRODUCTION LINE
  • CEMENT GRINDING STATION
  • CEMENT PRODUCTION LINE
  • LIME SLAKING PLANT
  • MAGNESIUM OXIDE (MgO) PLANT
  • LITHIUM PRODUCTION LINE
  • GYPSUM POWDER PRODUCTION LINE
  • ALUMINUM ASH PROCESSING SYSTEM
  • FRACTURING PROPPANT PRODUCTION LINE
  • SOLID (HAZARDOUS) WASTE INCINERATION SYSTEM
  • PULVERIZED COAL PREPARATION PRODUCTION LINE
  • GGBS PRODUCTION LINE
  • SUPERPHOSPHATE PRODUCTION LINE
  • MOLECULAR SIEVE PRODUCTION LINE
  • FLUE GAS PURIFICATION SYSTEM
  • FGD SYSTEM
  • SOIL REMEDIATION SYSTEM
  • PHOSPHOGYPSUM DISPOSAL PRODUCTION LINE
  • PHOSPHATE ORE DRESSING LINE
  • PHOSPHATE ORE PELLETIZATION PRODUCTION PROCESS
  • Grinding Mills
  • Kilns & Dryers
  • Granulators
  • Conveyors
  • Crushers
  • Bucket Elevators
  • Project details

    Project Name

    100,000 t/a Briquette Project in Hami, Xinjiang

    Capacity

    100,000 t/a

    Location

    Hami, Xinjiang, China

    Project Overview

    Project address: China•Xinjiang•Hami

    Construction unit: Hami Blue Huoyan New Energy Development Co., Ltd.

    Product name: briquette screening and conveying

    Production scale: 100,000 tons of briquette production line per year

    Service scope: from raw material storage and transportation, screening, transportation to finished product storage and transportation system equipment


    Project Solution

    Design Principles

    (1) On the premise of meeting the requirements of production scale, the host adopts stand-alone, single-line equipment to achieve the purpose of smooth and compact production line, save land, and increase land use rate.

    (2) The auxiliary equipment is based on the principles of stability, reliability, and energy saving to ensure normal production, high quality, high yield, and low energy consumption.

    (3) Fully integrate the local natural conditions, optimize the design plan under the process and production conditions, and reduce the project cost as much as possible.

    (4) Conscientiously implement the relevant national environmental protection, laws, regulations and standards, strictly control environmental pollution, reduce pollutant discharge, protect and improve the environment, and realize safe and civilized production.

     

    Project Implementation

    After the contract was signed, our company concentrated its strengths and made equipment. With the strong support and cooperation of the owner, the project was put into operation on June 20. After more than 20 days of commissioning, it successfully reached the production standard and was highly praised and affirmed by the owner. 

    Related Equipment

    10 sets of Double shaft mixer (ZJ400×6m), 10 sets of Vibrating screen (YK1230)

    Contact Us

    Please leave a message. Get answers next business day.

    Name *

    Email *

    Telephone

    Message *

    Send message & get quote